Jump to content

英文维基 | 中文维基 | 日文维基 | 草榴社区

Masaka–Mutukula Road

From Wikipedia, the free encyclopedia

Masaka–Mutukula Road
Route information
Length56 mi (90 km)
Major junctions
North endMasaka
Major intersectionsKalisizo
Kyotera
Kakuuto
South endMutukula
Location
CountryUganda
Highway system

Masaka–Mutukula Road is a road in the Central Region of Uganda, connecting the city of Masaka, in Masaka District, to the border town of Mutukula in Kyotera District.[1]

Location

[edit]

The road stars in Masaka, near the Uganda Police barracks, where this road forms a T-junction with Broadway Road.[2] The road continues in a southwesterly direction, through Kalisizo, Kyotera and ends in Mutukula, at the international border with Tanzania, a total length of about 90 kilometres (56 mi).[3]

Overview

[edit]

This road is part of the East African Community Road Network Project. It is the main road transport corridor between Uganda and Tanzania. The road is divided into two sections: (a) Masaka–Kyotera section, which measures 44 kilometres (27 mi), was built in 1960s and has begun to deteriorate and (b) Kyotera–Mutukula section, measuring 46 kilometres (29 mi), was originally constructed in the 1960s and was upgraded to class II bitumen standards in 2003 with a loan from the African Development Bank (AfDB).[4] Section (b) was in good condition, as of 2006, while section (a) was in need of an upgrade.[5]

Upgrade and expansion

[edit]

In January 2020, the government of Uganda began preparations to upgrade and expand the road, using funds sourced from the African Development Bank (AfDB). The single-carriageway road will be upgraded to class II bitumen surface, with culverts and drainage channels. The road width will be increased to 11 metres (36 ft). In the town of Kyotera, the width will be further increased to accommodate a 3 metres (10 ft) parking lane.[6]

The engineering, procurement and construction (EPC) contract was awarded to Chongqing International Construction Corporation (CICCO). Included in this contract is the upgrade to bitumen class II of the Masaka-Villa Maria Road measuring 11 kilometres (7 mi) and the tarmacking of another 7 kilometres (4 mi) of roads within Masaka City. The contract price is reported as UGX:691 billion (approx. US$179 million).[1]

CICCO entered into a 2-year pre-financing agreement with the government of Uganda (GoU). For the first two years the company will use its own money. The road also received funding from the AfDB, in form of a loan to the GoU. Completion of the upgrade is anticipated in 2028.[1]

See also

[edit]

References

[edit]
  1. ^ a b c Uganda Radio Network (21 March 2024). "Government commissions Masaka-Kyotera-Mutukula road works". The Independent (Uganda). Kampala, Uganda. Retrieved 23 March 2024.
  2. ^ "Location of Beginning of Masaka–Mutukula Road" (Map). Google Maps. Retrieved 23 March 2024.
  3. ^ "Distance Between Masaka Police Barracks, Masaka, Central Region, Uganda and Mutukula, Uganda" (Map). Google Maps. Retrieved 23 March 2024.
  4. ^ Eddie Ssejjoba (7 July 2003). "Kyotera-Mutukula Road Will Boost Trade". New Vision. Kampala. Retrieved 13 May 2016.
  5. ^ EAC (June 2006). "East African Community: The East African Road Network Project: Project Status Briefs". Arusha: East African Community (EAC). Archived from the original on 24 March 2016. Retrieved 13 May 2016.{{cite web}}: CS1 maint: bot: original URL status unknown (link)
  6. ^ Ambrose Musasizi (28 January 2020). "Govt unveils plan to expand Masaka-Mutukula highway". Daily Monitor. Kampala, Uganda. Retrieved 28 January 2020.
[edit]