Jump to content

英文维基 | 中文维基 | 日文维基 | 草榴社区

SIAC Construction Ltd v Mayo County Council

From Wikipedia, the free encyclopedia

SIAC Construction Ltd v The County Council of the County of Mayo
CourtSupreme Court of Ireland
CitationSIAC Construction Ltd. v. Mayo County Council [2002] IESC 39 (9 May 2002)
Case history
Appealed fromSIAC Construction Ltd v The County Council of the County of Mayo
Appealed toSupreme Court
Court membership
Judge sittingKeane C.J./ Denham J. / Murray J. / Hardiman J. / Fennelly J.
Case opinions
The Supreme Court rejected the appeal and affirm the order of the High Court.
Keywords
Invitation to tender, tender invitation to most economically advantageous, whether responded adequately explained decision to award contract to party other than lowest tenderer, discretion of awarding authority, Council Directive 71/305/E.E.C.

SIAC Construction Ltd v The County Council of the County of Mayo [2002] IESC 39,[1] [2002] 3 IR 148 was a case in which the Supreme Court of Ireland ruled that, in exercising its margin of discretion in the area of public procurement, a tender awarding authority is required to respect the general principles of equality, transparency and objectivity.[2][3]

Background

[edit]

On the 1992 Mayo County Council advertised an open procedure for a public work contract. In advertisement Council noted that they not going to make a decisions based on "lowest price only" the preference will be based on "most economically advantageous" tender. SIAC Construction tender for the provision of a new sewerage system for town of Ballinrobe. SIAC made the lowest tender.

Mayo County Council employed a consulting engineer, who reported that Pat Mulcair might prove "at the end of the day to be the lowest.[4] SIAC Construction took Mayo County Council to the High Court of judicial review stating that Council acted in breach of awarding the contract, to other party, in respect of public requirements.

On 11 October 1993, SIAC made an application to the High Court concerning of a decision made be the Mayo County Council not to award a construction contract. Judge Laffoy on 17 June 1997 decided that SIAC is not entitled to any reliefs.

At that point SIAC made an application to the Supreme Court. Subsequently, a reference was submitted to the European Court of Justice on 18 October 2001 to clarify the Article 29 of Council Directive 71/305/EEC of 26 July 1971.

High Court decision

[edit]

SIAC claimed that Mayo County Council were in breach of the European Communities Directive 71/305/EEC (as now consolidated in Directive 93/37/EEC) and/or the European Communities (Award of Public Works Contracts) Regulations, 1992 (S.I. No. 36 of 1992).[5]

On 17 June 1997 High Court decide that SIAC is not entitled to any reliefs. Mayo County Council is not liable in damages to the SIAC Construction Ltd for breach of the 1971 Council Directive and 1992 Regulations.[6]

Court of Justice of the European Union

[edit]

The Court of Justice of the European Union received a question concerning the interpretation of Article 29 of Council Directive 71/305/EEC of 26 July 1971[6] in relation to the procedures for the award of public works contracts between SIAC Construction Ltd and the County Council of Mayo.

The Court of Justice of the European Communities gave its judgment on 18 October 2001, where it was explained that Article 29 of Council Directive 71/305/EEC of 26 July 1971[6] could be interpreted for the benefit of County Council Mayo as to whether the criteria on the award was clearly stated in the contract notice and decision made on professional opinion based on objective factors.[7] The European Court concluded that such an interpretation is a matter for the national court.

Holding of the Supreme Court

[edit]

SIAC was seeking to rely on the judgment of the European Court to pursue issues which were not dealt in the appeal of the High Court. County Council advertised tender "most economically advantageous"[8] and not to be made on the basis of "lowest price only."[8] SIAC submitted lowest price, therefore the consulting engineer employed by County Council reported that Pat Mulcair might prove "at the end of the day to be the lowest."[7] SIAC claimed that the engineer did not acted objectively and his estimates were wrong. The Supreme Court ruled that County Council acted within the margin of discretion by choosing right tender. The engineer approached calculations correctly. The Supreme Court rejected the appeal and affirm the order of the High Court.[8]

References

[edit]
  1. ^ "SIAC Construction Ltd. v. Mayo County Council [2002] IESC 39 (9 May 2002)". www.bailii.org. Retrieved 15 May 2020.
  2. ^ "Public works contracts". McGarr Solicitors. 28 May 2008.
  3. ^ "Evaluated: Supreme Court provides clarity on the review of public procurement processes". Philip Lee Solicitors. 7 June 2019.
  4. ^ SIAC Construction Ltd, Applicant, v The County Council of the County of Mayo, Respondent - [2002] 3 IR 148
  5. ^ "Siac Construction v. Mayo County Council [1997] IEHC 97 (17th June, 1997)". www.bailii.org.
  6. ^ a b c "Council Directive". 26 July 1971.
  7. ^ a b "Court of Justice of the European Communities". British and Irish Legal Information Institute.
  8. ^ a b c "SIAC Construction Ltd. v. Mayo County Council [2002] IESC 39 (9th May, 2002)". British and Irish Legal Information Institute.